A466 closure - change of plan

Search

27th March 2020


There has been a change of plan
regarding the closure of the "valley road" which supersedes the information given below (on 21st March).

Brockweir Bridge south to Tintern Station: closed starting Tuesday March 31st until Monday 6th April (weekdays 0930 to 1330).

Brockweir Bridge north to Catchmays Court: postponed until further notice.


21st March 2020

Road Closure - between 16 March and 7 April 2020

The plan for Phase 2 of the A466 resurfacing programme will be to split the site into 2 stages in order to keep Brockweir Bridge open.

Stage one will be from Tintern to just short of Brockweir Bridge from 23rd March to 27th March, (pale blue line on map) and the road will be closed between the hours of 09:30 and 15:30. All resurfacing works will be completed by the end of 27th March at this location.

Stage two will be from the area in front of Brockweir Bridge (and including Brockweir Bridge) to Catchmays Court from 30th March to 7th April (green line on map), the road will be closed between the hours of 09:30 and 15:30 on weekdays only. This stage will complete the resurfacing works on the A466. 

Through Traffic to Chepstow or Monmouth will be diverted along the B4293 via Trellech.

Monmouthshire County Council’s Operations Team are undertaking the resurfacing works, so please direct any queries during the works to Stacey Harris or the Operations Team at contact@monmouthshire.gov.uk or 01633 644644.